Quiz Fun

1. According to AIA Document A701, Instructions to Bidders represents all of the following, with the exception of which statement?

A. The bidder has read and understands the bidding documents.

B. The bid complies with the bidding documents.

C. The bidder has visited the site and observed the conditions under which the work will be performed.

D. The bid is based, without exception, on the materials, equipment, and systems called for in the bidding documents.

E. The bidder has inspected the construction documents for any errors, inconsistencies, or ambiguities.

2. The need to provide for flexibility in the scope of a project can be accommodated by which of the following?

A. Alternates

B. Unit prices

C. Addenda

D. A and B

E. B and C

F. A, B, and C

3. A bidder wishes to substitute materials or services otherwise specified in the bidding documents and submits a request for approval in writing at least 10 days before the bid submission date. . An architect is required to:

A. Accept the substitution and notify all bidders by addendum.

B. Determine whether the proposed substitution is acceptable, and if so, notify all parties through addendum.

C. Determine whether the proposed substitution is acceptable, and notify that bidder only.

D. Issue an addendum postponing all bids until all bidders have a chance to review the substitution.

4. A bidder discovers an error or ambiguity in the bid documents and informs the architect at least seven days prior to the submission date. The architect should:

A. Thank the bidder and reward his or her helpfulness by not informing other bidders.

B. Discuss the issue at a pre-bid meeting with all bidders present.

C. Issue any changes or addenda that result from the inquiry to all bidders.

D. Issue an add-alternate or deduct-alternate to all bidders.

5. After bidding is complete and a contractor has been selected, which of the following is not a reasonable course of action.

A. The successful bidder should be informed in a way that does not form a legally binding agreement before contract documents are signed.

B. Bids of the next lowest bidders are returned or discarded.

C. The contractor asks for assurance that sufficient financial arrangements have been made to undertake the project.

D. The contractor furnishes names of proposed suppliers of materials and equipment, details of the amount of work to be undertaken by the contractor’s forces, and a list of intended subcontractors for the architect’s approval.

E. The contractor submits a bond in accordance with the owner’s requirements as expressed in the instruction to bidders.